TxDOT Bid Item 416-7040 Pricing — Drill Shaft (Rdwy Ill Pole) (30 In)

See what winning bidders charged, and which contractors bid this item.
Enter your quantity and county below.

What winning bidders charged for 416-7040

$295
Median price from winning bids (half the winners came in below it)
From 39 Texas lettings at 60–126 LF over 24 months.

Contractors who bid Item 416-7040

Price at a contractor's lowest and you have beaten them on this item. Price at their median and it is a coin flip. In price range, a short bar means they price this item consistently, a long one means it changes job to job.

Contractor
Bids
Price range
Lowest
Median
Highest
ISI CONTRACTING, INC.
1
$141
$141
$141
JASCO
1
$146
$146
$146
HARPER BROTHERS CONSTRUCTION LLC
3
$159
$209
$220
PULICE CONSTRUCTION, INC.
7
$162
$322
$500
E-Z BEL CONSTRUCTION, LLC
7
$165
$270
$375
SER CONSTRUCTION PARTNERS, LLC
2
$166
$197
$229
R CONSTRUCTION CIVIL, LLC
3
$168
$265
$290
REYES TX, INC.
2
$190
$204
$217
JAMES CONSTRUCTION GROUP, LLC
8
$194
$262
$553
↑ $295 Median price from winning bids
TxDOT public bid tabulations.
This is one bid item. Your letting has dozens.

Send your CSJ and we'll run this for every one.

We email it back within 24 hours. Free, and no account to create.

Pricing on the 10 lettings closest to 100 LF for Item 416-7040

Each letting shows the engineer's estimate, every bidder's price including the winner, how far each sat from the estimate, and their total bid. Selected from 39 lettings in the current filter.

SH 172 CONSTRUCT ROUNDABOUT 2909 Quantity 100.00 LF, same as yours
August 2026 · CSJ 0420-01-051
Engineer's est.STX CIVILWONHUNTER INDUSTRIES, LTD.E-Z BEL CONSTRUCTION, LLC
Price per LF$300$496$250$375
Line total$30,000$49,648$25,000$37,500
vs. estimate—+65%−17%+25%
Total bid—$5.3M$6.2M$7.9M
US 281: from FM 3027 to FM 3027 Quantity 100.00 LF, same as yours
August 2026 · CSJ 0249-08-046
Engineer's est.VACA UNDERGROUND UTILITIES INCWONJASCOSCOTT TUCKER CONSTRUCTION COMPANY, LLCHIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLCROAD SOLUTIONS L.L.C.WG ENGINEERING & CONSTRUCTION, LLCMARCOM'S MOWING SERVICE, LLCELECNOR BELCO ELECTRIC, INC.SYNERGY SIGNS & SERVICES LLCFLORIDA TRAFFIC CONTROL DEVICES, INC.
Price per LF$300$225$146$221$241$300$355$400$422$500$526
Line total$30,000$22,500$14,600$22,100$24,107$30,000$35,500$40,000$42,200$50,000$52,600
vs. estimate—−25%−51%−26%−20%0%+18%+33%+41%+67%+75%
Total bid—$180,930$196,175$230,588$190,408$258,914$239,909$242,100$251,914$221,832$303,000
We clean the data. You set the price.

Every item on your bid, laid out like this.

We email it back within 24 hours. Free, and no account to create.

TxDOT average low bid prices for Item 416-7040

TxDOT's weighted average unit price for this item across 24 months of lettings. A market reference, not a bid price.

Statewide
Weighted average unit price
all bidders
$349
Weighted average low unit price
winning bids only
$330

Frequently asked questions about TxDOT Item 416

What is TxDOT bid item 416-7040?

Item 416-7040 covers Drill Shaft (Rdwy Ill Pole) (30 In) under TxDOT Item 416, Drilled Shaft Foundations.

What should I bid on 416-7040?

The median winning bid across 39 Texas lettings at 60–126 LF over 24 months is $295. Where you land depends on your cost and how tight the competition is.

What did contractors actually charge for 416-7040?

Winning bids ranged from $141 to $553 across 9 contractors, with a median of $295.

What is the average low bid price for 416-7040?

$330 statewide, weighted across all winning bids.

What is the weighted average unit price for 416-7040?

$349 statewide, across all bidders, not just winners.

Why is the average different from the median winning bid?

The average includes every bid, winning and losing, weighted by quantity. The median winning bid only counts the price that won each letting.

How does 416-7040 pricing change with quantity?

This page bands results by quantity so different job sizes aren't averaged together. Larger quantities generally price lower per unit.

Which contractors bid 416-7040 most often?

JAMES CONSTRUCTION GROUP, LLC, E-Z BEL CONSTRUCTION, LLC, PULICE CONSTRUCTION, INC. are among the most frequent bidders on this item in the current window.

What is the lowest price anyone has bid on 416-7040?

$141 per LF, from ISI CONTRACTING, INC..

How much do bids vary on 416-7040?

From $141 to $553 per LF across 9 contractors, before excluding near-zero outliers.

Why do some bids on 416-7040 come in near zero?

A near-zero bid on one item is usually priced below market and recovered elsewhere on the bid. Near-zero bids are excluded from the figures on this page when present.

Does 416-7040 pricing differ by district?

Weighted average unit price is $349 statewide under All counties. Select a county to compare local pricing against the statewide average.

Has 416-7040 pricing gone up or down?

This page reflects the last 24 months of lettings. Check back as new lettings publish; pricing updates on the same schedule as the rest of the bid tabulation tools.

How many TxDOT projects used 416-7040 in the last 24 months?

39 lettings in Texas carried this item in the current window.

How competitive is bidding on 416-7040?

9 contractors bid this item across 39 lettings, with prices spanning $141 to $553 per LF.