| Engineer's est. | MC2 CIVIL, LLCWON | FORDE CONSTRUCTION COMPANY, INC. | C. E. BARKER, LTD. | ENVIRONMENTAL ALLIES, INC. | |
|---|---|---|---|---|---|
| Price per LF | $4.00 | $3.00 | $2.35 | $3.03 | $5.00 |
| Line total | $3,332.00 | $2,499.00 | $1,957.55 | $2,523.99 | $4,165.00 |
| vs. estimate | — | −25% | −41% | −24% | +25% |
| Total bid | — | $20M | $29M | $28M | $24M |
TxDOT Bid Item 542-6001 Pricing — Remove Metal Beam Guard Fence
See what winning bidders charged, and which contractors bid this item.
Enter your quantity and county below.
What winning bidders charged for 542-6001
$2.95
Median price from 8 winning bids (half came in below it)
From 8 Texas lettings at 650–19510 LF over 24 months.
Contractors who bid Item 542-6001
Price at a contractor's lowest and you have beaten them on this item. Price at their median and it is a coin flip. In price range, a short bar means they price this item consistently, a long one means it changes job to job.
Contractor
Bids
Price range
Lowest
Median
Highest
JAMES CONSTRUCTION GROUP, LLC
3
$0.75
$2.50
$4.00
WEBBER, LLC
5
$0.75
$2.25
$4.00
PULICE CONSTRUCTION, INC.
3
$0.85
$1.87
$2.12
CK NEWBERRY, LLC
1
$2.00
$2.00
$2.00
FLUOR HEAVY CIVIL, LLC
1
$2.04
$2.04
$2.04
POSILLICO CIVIL, INC.
2
$2.09
$2.55
$3.00
AUSTIN BRIDGE & ROAD SERVICES, LP
2
$2.11
$2.16
$2.20
SUNDT CONSTRUCTION, INC.
1
$2.14
$2.14
$2.14
MARIO SINACOLA & SONS EXCAVATING, INC.
1
$2.25
$2.25
$2.25
↑ $2.95 Median price from winning bids
TxDOT public bid tabulations.
This is one bid item. Your letting has dozens.
Send your CSJ and we'll run this for every one.
We email it back within 24 hours. Free, and no account to create.
Pricing on the 8 lettings for Item 542-6001
Each letting shows the engineer's estimate, every bidder's price including the winner, how far each sat from the estimate, and their total bid.
IH 45 at Cullen Pump Station Quantity 833.00 LF
US 79 AT LITTLE BRAZOS RIVER - BR Quantity 1050.00 LF
| Engineer's est. | LARRY YOUNG PAVING, INC.WON | JAMES CONSTRUCTION GROUP, LLC | BIG CREEK CONSTRUCTION, LTD. | MORTMARA CONSTRUCTION, INC. | TEXAS MATERIALS GROUP, INC. | |
|---|---|---|---|---|---|---|
| Price per LF | $3.00 | $3.25 | $2.50 | $3.00 | $3.00 | $3.00 |
| Line total | $3,150.00 | $3,412.50 | $2,625.00 | $3,150.00 | $3,150.00 | $3,150.00 |
| vs. estimate | — | +8% | −17% | 0% | 0% | 0% |
| Total bid | — | $19M | $23M | $19M | $29M | $19M |
We clean the data. You set the price.
Every item on your bid, laid out like this.
We email it back within 24 hours. Free, and no account to create.
TxDOT average low bid prices for Item 542-6001
TxDOT's weighted average unit price for this item across 24 months of lettings. A market reference, not a bid price.
| Statewide | |
|---|---|
Weighted average unit price all bidders | $2.38 |
Weighted average low unit price winning bids only | $2.41 |
Frequently asked questions about TxDOT Item 542
What is TxDOT bid item 542-6001?
Item 542-6001 covers Remove Metal Beam Guard Fence under TxDOT Item 542, Removing Metal Beam Guard Fence.
What should I bid on 542-6001?
The median of 8 winning bids across Texas lettings at 650–19510 LF over 24 months is $2.95. Where you land depends on your cost and how tight the competition is.
What did contractors actually charge for 542-6001?
Winning bids ranged from $0.75 to $4.00 across 9 contractors, with a median of $2.95.
What is the average low bid price for 542-6001?
$2.41 statewide, weighted across all winning bids.
What is the weighted average unit price for 542-6001?
$2.38 statewide, across all bidders, not just winners.
Why is the average different from the median winning bid?
The average includes every bid, winning and losing, weighted by quantity. The median winning bid only counts the price that won each letting.
How does 542-6001 pricing change with quantity?
This page bands results by quantity so different job sizes aren't averaged together. Larger quantities generally price lower per unit.
Which contractors bid 542-6001 most often?
WEBBER, LLC, JAMES CONSTRUCTION GROUP, LLC, PULICE CONSTRUCTION, INC. are among the most frequent bidders on this item in the current window.
What is the lowest price anyone has bid on 542-6001?
$0.75 per LF, from JAMES CONSTRUCTION GROUP, LLC.
How much do bids vary on 542-6001?
From $0.75 to $4.00 per LF across 9 contractors, before excluding near-zero outliers.
Why do some bids on 542-6001 come in near zero?
A near-zero bid on one item is usually priced below market and recovered elsewhere on the bid. Near-zero bids are excluded from the figures on this page when present.
Does 542-6001 pricing differ by district?
Weighted average unit price is $2.38 statewide under All counties. Select a county to compare local pricing against the statewide average.
Has 542-6001 pricing gone up or down?
This page reflects the last 24 months of lettings. Check back as new lettings publish; pricing updates on the same schedule as the rest of the bid tabulation tools.
How many TxDOT projects used 542-6001 in the last 24 months?
8 lettings in Texas carried this item in the current window.
How competitive is bidding on 542-6001?
9 contractors bid this item across 8 lettings, with prices spanning $0.75 to $4.00 per LF.