TxDOT Bid Item 542-7002 Pricing — Remove Terminal Anchor Section

See what winning bidders charged, and which contractors bid this item.
Enter your quantity and county below.

What winning bidders charged for 542-7002

$279
Median price from winning bids (half the winners came in below it)
From 34 Texas lettings at 4 EA over 24 months.

Contractors who bid Item 542-7002

Price at a contractor's lowest and you have beaten them on this item. Price at their median and it is a coin flip. In price range, a short bar means they price this item consistently, a long one means it changes job to job.

Contractor
Bids
Price range
Lowest
Median
Highest
GARRET SHIELDS INFRASTRUCTURE
4
$100
$500
$1,000
RHINO EQUITY, LLC
2
$100
$300
$500
THK CONSTRUCTION LLC
3
$100
$158
$165
HUNTER INDUSTRIES, LTD.
7
$125
$250
$655
TEXAS MATERIALS GROUP, INC.
9
$125
$220
$577
CK NEWBERRY, LLC
5
$135
$500
$550
ALTUS CONSTRUCTION LLC
4
$139
$216
$237
ANDERSON COLUMBIA CO., INC.
3
$140
$215
$300
ALLEN KELLER COMPANY
1
$142
$142
$142
↑ $279 Median price from winning bids
TxDOT public bid tabulations.
This is one bid item. Your letting has dozens.

Send your CSJ and we'll run this for every one.

We email it back within 24 hours. Free, and no account to create.

Pricing on the 10 lettings closest to 4 EA for Item 542-7002

Each letting shows the engineer's estimate, every bidder's price including the winner, how far each sat from the estimate, and their total bid. Selected from 34 lettings in the current filter.

Bridge Replacement Anderson Creek Quantity 4.00 EA, same as yours
September 2026 · CSJ 0722-03-016
Engineer's est.LONGVIEW BRIDGE AND ROAD, LTD.WONGARRET SHIELDS INFRASTRUCTURETHK CONSTRUCTION LLCEAST TEXAS BRIDGE, INC.DRAKE COMPANIES LLCRB CONTRACTING, LLCHIGHWAY 19 CONSTRUCTION LLCHODGES AND SON CONSTRUCTION COMPANY, INC.
Price per EA$200$165$100$158$165$175$225$250$500
Line total$800$660$400$630$660$700$900$1,000$2,000
vs. estimate—−17%−50%−21%−17%−12%+13%+25%+150%
Total bid—$1.5M$1.8M$1.5M$1.7M$1.6M$1.7M$1.7M$1.8M
FY27 - Freestone BPM - 09 Quantity 4.00 EA, same as yours
August 2026 · CSJ 6501-02-001
Engineer's est.GARRET SHIELDS INFRASTRUCTUREWONODUM SERVICES, LLCRHINO EQUITY, LLC
Price per EA$300$500$250$500
Line total$1,200$2,000$1,000$2,000
vs. estimate—+67%−17%+67%
Total bid—$144,678$149,285$231,695
We clean the data. You set the price.

Every item on your bid, laid out like this.

We email it back within 24 hours. Free, and no account to create.

TxDOT average low bid prices for Item 542-7002

TxDOT's weighted average unit price for this item across 24 months of lettings. A market reference, not a bid price.

Statewide
Weighted average unit price
all bidders
$390
Weighted average low unit price
winning bids only
$365

Frequently asked questions about TxDOT Item 542

What is TxDOT bid item 542-7002?

Item 542-7002 covers Remove Terminal Anchor Section under TxDOT Item 542, Removing Metal Beam Guard Fence.

What should I bid on 542-7002?

The median winning bid across 34 Texas lettings at 4 EA over 24 months is $279. Where you land depends on your cost and how tight the competition is.

What did contractors actually charge for 542-7002?

Winning bids ranged from $100 to $1,000 across 9 contractors, with a median of $279.

What is the average low bid price for 542-7002?

$365 statewide, weighted across all winning bids.

What is the weighted average unit price for 542-7002?

$390 statewide, across all bidders, not just winners.

Why is the average different from the median winning bid?

The average includes every bid, winning and losing, weighted by quantity. The median winning bid only counts the price that won each letting.

How does 542-7002 pricing change with quantity?

This page bands results by quantity so different job sizes aren't averaged together. Larger quantities generally price lower per unit.

Which contractors bid 542-7002 most often?

TEXAS MATERIALS GROUP, INC., HUNTER INDUSTRIES, LTD., CK NEWBERRY, LLC are among the most frequent bidders on this item in the current window.

What is the lowest price anyone has bid on 542-7002?

$100 per EA, from THK CONSTRUCTION LLC.

How much do bids vary on 542-7002?

From $100 to $1,000 per EA across 9 contractors, before excluding near-zero outliers.

Why do some bids on 542-7002 come in near zero?

A near-zero bid on one item is usually priced below market and recovered elsewhere on the bid. 6 such bids are excluded from every figure on this page.

Does 542-7002 pricing differ by district?

Weighted average unit price is $390 statewide under All counties. Select a county to compare local pricing against the statewide average.

Has 542-7002 pricing gone up or down?

This page reflects the last 24 months of lettings. Check back as new lettings publish; pricing updates on the same schedule as the rest of the bid tabulation tools.

How many TxDOT projects used 542-7002 in the last 24 months?

34 lettings in Texas carried this item in the current window.

How competitive is bidding on 542-7002?

9 contractors bid this item across 34 lettings, with prices spanning $100 to $1,000 per EA.