TxDOT Item 672 Raised Pavement Markers: Bid Code Spec, Pricing and Performance Requirements

Item 672 covers furnishing and installing raised pavement markers, and it also covers removing the old ones. That's the answer to a question Item 677 leaves open: Item 677 doesn't pay for RPM removal, but Item 672 does. The spec says RPM removal follows Item 677's process "except for measurement and payment," and the payment clause makes it official: removing existing markers and installing new ones are priced together, as one number. So if you've been treating RPM removal as a cost with no clear home, it isn't missing, it's already built into this item's price. This covers the 6 bid codes that show up most often across recent TxDOT lettings, what separates one marker type from another, and what the 30-day performance obligation actually does and doesn't put on you.
Try the free bid item pricing tool → Jump to pricing ↓

TxDOT Item 672 Bid Code Variants: What Determines Pricing

Item 672 pays for RPMs "of the types specified," and the spec defines nine of them across three material categories, though only three show up in this data. Two things determine what you're actually pricing:
  • Marker type. I-C, II-A-A, and II-C-R are the three types in this data, all Reflectorized Pavement Markers. I-C retroreflects white light on a single approach face. II-A-A retroreflects amber on both approach and trailing faces. II-C-R retroreflects white on approach and red on trailing, the only one of the three requiring two different colors from a single unit. Six more named types exist in the broader spec, Traffic Buttons and Plowable markers among them, not represented in this specific dataset.
  • Which code series, and the gap isn't uniform even within this one item. 672-6007 and 672-7002 are both "REFL PAV MRKR TY I-C," priced 50 percent apart. 672-6009 and 672-7004, both "TY II-A-A," price identically. 672-6010 and 672-7006, both "TY II-C-R," sit 20 percent apart. Same item, three different relationships between the two series. Confirm which one applies to your specific code rather than assuming a flat premium carries across all three types.

TxDOT Item 672 Pricing: Key Takeaways

  • RPM removal is bundled into this item's price, not a separate cost or a gap. Item 677 explicitly excludes it. Item 672's own payment clause explicitly includes it, "removing existing markers" alongside furnishing and installing new ones.
  • The 30-day performance obligation has a real exclusion, not just a requirement. Failures caused by extreme wear, snow or ice removal, or pavement failure can be excluded from your replacement obligation, at the Engineer's determination.
  • No additional payment for performance-period replacements that aren't excluded. If a marker fails from defective material or bad installation within 30 days, replacing it is on you, free.
  • Adhesive choice is temperature-gated, not a preference. Bituminous needs 40°F or higher. Epoxy needs 50°F or higher, and it's required, not optional, for plowable markers.
  • This is a plans quantity item, same measurement basis as Items 666 and 677.

Cost Factors for TxDOT Item 672 Raised Pavement Markers

Cost Factors That Vary by Bid Code

Work through these one code at a time. They're what makes 672-7006 a different number than 672-7002.
  • Marker type and face count. Single-face types like I-C need one retroreflective element. Dual-face types like II-A-A and II-C-R need two, and II-C-R specifically needs two different colors on those two faces, white approach, red trailing, a more complex manufacturing spec than a single-color dual-face marker.
  • Adhesive system. Bituminous adhesive works on bituminous pavements. Epoxy adhesive works on hydraulic cement concrete, and is required, not optional, for plowable markers regardless of surface. Different adhesive, different application temperature floor, different cost.
  • Whether the surface needs preparation first. Bond surfaces have to be free of dirt, curing compound, grease, oil, moisture, and loose or unsound existing markings before adhesive goes down. A surface that needs real prep work costs more to install on than one that doesn't, independent of which marker type is going down.
  • Manufacturer consistency within a class. The spec requires furnishing RPMs for each class from the same manufacturer. That's a sourcing constraint worth pricing into a job with mixed marker classes, not a free assumption that any approved source works interchangeably.

Cost Factors That Apply to Every TxDOT Item 672 Bid Code

These don't separate one marker type from another. They sit under all of them.
  • 100% bonding contact is the installation standard, not a target.
    "Ensure that 100% of the bonding area of RPMs is in contact with the adhesive, and ensure that RPMs, except for plowable markers, are seated on a continuous layer of adhesive and not in contact with the pavement surface."
    That's a checkable, binary standard, not a "mostly bonded" tolerance.
  • Application temperature is a hard floor, both directions. Bituminous adhesive applies only when pavement and RPM temperature are 40°F or higher, and never heated above 400°F. Epoxy applies only when pavement temperature is 50°F or higher. Both need continuous or machine mixing before application.
  • Guide marks for placement can't be permanent.
    "Establish pavement marking guides to mark the lateral location of RPMs as shown on the plans and as directed. Do not make permanent marks on the roadway for the guides."
  • Misaligned markers get removed and replaced at your expense.
    "If necessary, remove and replace RPMs placed out of alignment or sequence... at the Contractor's expense in accordance with Item 677 (except for measurement and payment)."
    Same Item 677 removal process referenced again, same "except measurement and payment" carve-out, meaning the correction cost lives here too.

TxDOT Item 672 Payment Terms: Subsidiary Work vs. Separately Paid Items

This is the item that answers the question Item 677 leaves open. Read them together, not separately, and the scope resolves cleanly.
What's bundled into the unit price, all of it, one number:
"This price is full compensation for removing existing markers; furnishing and installing RPMs; and materials, equipment, labor, tools, and incidentals."
Removing what's there and installing what's new, priced as one action, not two.
No additional payment for performance failures that aren't excluded.
"No additional payment will be made for replacement of RPMs failing to meet the performance requirements."
That's a direct cost on you for the specific failures the spec holds you responsible for, covered next.
Sampling is the Engineer's cost to administer, not yours to arrange. The spec assigns sampling to the Engineer, under Tex-729-I, a procedural detail worth knowing so you're not budgeting for third-party sampling coordination that isn't your responsibility.

TxDOT Item 672 Performance Requirements: The 30-Day Obligation and Its Exclusions

Item 672 carries a real post-installation obligation, similar in shape to Item 666's retroreflectivity requirement, but with a genuinely fair provision Item 666 doesn't carry, an explicit exclusion for causes outside your control.
The baseline obligation.
"All RPMs must meet performance requirements for at least 30 calendar days after installation."
Failures get replaced within 30 days of notice, and the clock doesn't reset when the performance period ends.
"Replace all missing or non-reflective RPMs identified during the performance period within 30 days after notification. The end of the performance period does not relieve the Contractor from the performance deficiencies requiring corrective action identified during the performance period."
A deficiency flagged on day 29 still has to be fixed, even after day 30 has passed.
The exclusion is the part worth knowing exists.
"The Engineer may exclude RPMs from the replacement provisions of the performance, provided the Engineer determines the failure is a result of causes other than defective material or inadequate installation procedures. Examples of outside causes are extreme wear at intersections, damage by snow or ice removal, and pavement failure."
Not every failure in the 30-day window is automatically your cost. Traffic wear at a busy intersection, snowplow damage, or the pavement itself failing underneath a properly installed marker can all be grounds for exclusion, at the Engineer's determination.
You have a real right to be present for the evaluation.
"Upon request, the Engineer will allow a Contractor representative to accompany the Engineer on these evaluations."
Given the exclusion determination is the Engineer's judgment call, having your own representative present during the visual evaluation is worth exercising, not assuming happens automatically.

Pricing Considerations for Performance Requirements

  • Carry a replacement contingency sized to genuine installation risk, not total marker count. The exclusion provision means well-installed markers lost to intersection wear or snowplow damage aren't automatically on you, so a blanket "replace X percent" assumption overstates real exposure.
  • Request the field evaluation walk-through when a failure determination is being made. It's a spec'd right, not a courtesy, and it directly affects whether a given failure lands on you or gets excluded.
  • Price 100% bonding contact and correct application temperature as defect prevention, not overhead. Both are explicit standards an inspector can check directly, and failures traced to either fall outside the exclusion, defective installation is exactly what stays your responsibility.

TxDOT Item 672 Bid Item Pricing Data

Average unit price across TxDOT lettings over the last 24 months. Each code links to its full pricing page, where you can see the spread by competitor, by district, and by quantity band.
Bid item Code Item name Bid item average price Detailed pricing
REFL PAV MRKR TY I-C 672-6007 Raised Pavement Markers $6 View pricing →
REFL PAV MRKR TY II-A-A 672-6009 Raised Pavement Markers $4 View pricing →
REFL PAV MRKR TY II-C-R 672-6010 Raised Pavement Markers $6 View pricing →
REFL PAV MRKR TY I-C 672-7002 Raised Pavement Markers $4 View pricing →
REFL PAV MRKR TY II-A-A 672-7004 Raised Pavement Markers $4 View pricing →
REFL PAV MRKR TY II-C-R 672-7006 Raised Pavement Markers $5 View pricing →

Pricing Analysis: Key Cost Comparisons Across TxDOT Item 672

These prices are whole-dollar figures, worth flagging before drawing conclusions from them. At $4 to $6, a one-dollar difference is a large percentage swing. Treat the ratios below as directional, not precise, the way the same caution applied to Item 677's data before more precise figures became available.
6xxx prices at or above 7xxx on all three matched pairs, but not by a consistent amount.
Type 6xxx 7xxx Ratio
I-C$6$41.50x
II-A-A$4$41.00x
II-C-R$6$51.20x
This item joins Item 500 and Item 677 in showing 6xxx at or above 7xxx, the opposite of what Item 644 showed. Direction still isn't something to assume carries from one item to the next, but within this item, 6xxx is consistently the higher or equal number, never lower.
Type-to-type pricing within 7xxx sits close together, with II-C-R the highest of the three. I-C and II-A-A both average $4, II-C-R averages $5. Consistent with II-C-R being the only type here requiring two different retroreflective colors on one unit, though at this precision, treat the gap as suggestive rather than confirmed.

Executing TxDOT Item 672: Avoiding Rework and Ensuring Payment

For whoever's running the job. Same spec, stated as things to do.

Rework Triggers Under TxDOT Item 672

  • Less than 100% bonding area contact with adhesive, or a marker seated against the pavement surface instead of a continuous adhesive layer
  • Bituminous adhesive applied below 40°F, or heated above 400°F
  • Epoxy adhesive applied below 50°F, or on plowable markers where epoxy wasn't used at all
  • Markers placed out of alignment or sequence relative to the established guides
  • Missing, broken, or non-reflective markers identified during the 30-day performance period and not excluded for outside causes

Field Compliance Requirements for TxDOT Item 672

  • Bond surfaces confirmed free of dirt, curing compound, grease, oil, moisture, and loose or unsound existing markings before adhesive application
  • Guides marked for lateral placement without leaving permanent marks on the roadway
  • Bituminous adhesive machine-agitated continuously before application for even heat distribution
  • Epoxy adhesive machine-mixed before application
  • RPMs placed immediately after adhesive application to ensure proper bonding

Pay Application Requirements for TxDOT Item 672

  • Document removal and installation as one action per marker, since the payment clause bundles both into a single unit price, not two separate line items
  • Request the evaluation walk-through in writing when a performance failure is identified, since that's how the exclusion provision actually gets exercised in practice
  • Track manufacturer consistency per class, since the spec requires same-manufacturer sourcing within each RPM class on a project
  • Keep the 30-day notification-to-replacement window documented, since that timeline applies regardless of when in the performance period the deficiency was identified
Built for people pricing and executing TxDOT raised pavement marker work
Lead Estimators
Price RPM removal as part of this item, not as a separate line hunting for a home. Confirm which of the nine marker types you're actually bidding, three price close together in this data but the broader spec includes traffic buttons and plowable markers with real cost differences of their own.
Marker type spread, item 672
Price range
$4 to $6
II-C-R prices highest, the only type needing two colors on one unit
RPM removal lives here
Not a gap between two items
Project Managers and Project Engineers
Exercise your right to accompany the Engineer on performance evaluations. The exclusion for outside-cause failures, intersection wear, snowplow damage, pavement failure, only protects you if it gets applied correctly, and being present for the determination is how you make sure it does.
Performance obligation, item 672
Minimum window
30 days
The clock does not reset when the window closes
Exercise the walk-through right
Be present when the Engineer evaluates a failure
Owners
The real question on this item isn't whether markers will fail within 30 days, some will, it's whether failures get correctly sorted into "contractor's cost" and "outside cause." That determination happens in the field, at the Engineer's judgment, which makes the contractor's presence at evaluations a real risk-management detail, not a formality.
Contractor cost vs excluded cause
Engineer determination
Intersection wear, snowplow damage, and pavement failure can be excluded
A field judgment call
Not an automatic charge on every failure

Frequently asked questions about TxDOT Item 672

What is TxDOT Item 672, Raised Pavement Markers?

It's the TxDOT spec covering furnishing and installing RPMs, including reflectorized markers, traffic buttons, and plowable markers, along with the adhesive requirements, installation standards, and 30-day performance obligation that apply to them.

Is RPM removal paid separately from installation?

No. Item 672's own payment clause bundles "removing existing markers" together with furnishing and installing new ones into a single unit price. Item 677 explicitly excludes RPM removal from its own scope, and Item 672 is where that cost actually lives.

What happens if an RPM fails within 30 days of installation?

It has to be replaced within 30 days of notification, at no additional payment, unless the Engineer determines the failure resulted from something other than defective material or bad installation, extreme intersection wear, snow or ice removal damage, or pavement failure are named examples of exclusions.

Can I be present when the Engineer evaluates a failed marker?

Yes, upon request, a Contractor representative can accompany the Engineer on these evaluations.

What's the difference between adhesive types for RPM installation?

Bituminous adhesive is used on bituminous pavements, applied only at 40°F or higher, never heated above 400°F. Epoxy adhesive is used on concrete pavements, applied only at 50°F or higher, and is required for plowable markers regardless of surface.

What does "100% bonding area contact" actually require?

The entire bonding surface of the RPM has to be in contact with the adhesive, and except for plowable markers, the RPM has to sit on a continuous adhesive layer rather than touching the pavement surface directly.

Do all nine RPM types cost about the same?

Not necessarily. This data covers three reflectorized types priced within a couple dollars of each other. Traffic buttons and plowable markers, defined elsewhere in the spec, aren't represented in this dataset and may price differently.

How is Item 672 measured?

By each RPM, as a plans quantity item, paid at the proposal quantity unless modified through Article 9.2.

Does the end of the 30-day performance period end my replacement obligation?

No. A deficiency identified during the performance period still requires correction even after the 30 days has elapsed.

Is this pricing data free to use?

Yes. Every bid item pricing page linked above is free, no account needed.